How Long Does It Take to Develop a Custom Mold for Stainless Steel Sinks?
- Share
- Issue Time
- Aug 20,2025
For new mold development, the typical timeline is:
Design & Engineering: 1–2 weeks
Mold Manufacturing: 3–5 weeks
Sample Production & Approval: 1–2 weeks
Total: 4–8 weeks
Once approved, production batches can be completed in 1–2 days, with flexible delivery options (4–6 weeks for standard orders).